Swinerton Renewable Energy has completed the 18 MW Westlands Solar Farms project near Huron, Calif. Swinerton built the photovoltaic array and new substation on 85 acres adjacent to Interstate 5 under contract from Clenera.

The Westlands facility includes more than 77,000 JinkoSolar PV modules mounted on Array Technologies DuraTrack HZ single-axis tracking systems. The project includes 18 Advanced Energy AE 1000NX inverters.

The plant is connected by a half-mile-long generation tie and transmission line from the substation into a new 70 kV switchyard. The project is producing and selling power under a power purchase agreement with Pacific Gas and Electric.

Hybrid Energy Innovations 2015

Latest Top Stories

Mining Companies Find Value In Solar And Wind Generation

Mining companies are finding that solar and wind generation can help them defray costs and stay profitable in inhospitable parts of the globe.


Global Solar Developer UGE Finds A Rainbow In Lower Oil Prices

Urban Green Energy CEO Nick Blitterswyk says fear of oil prices is natural but unwarranted. Short-term, cheap oil actually favors project development, and the long-term trends are all going solar's way.


Nexamp Wrangles Largest Mass. Managed Growth Project For 2014

The Boston-based developer had to hustle to complete the large-scale project in bad weather on difficult terrain.


e2/ECTA Helps Dealership Go Green With 310 kW Rooftop PV System

Haldeman Ford in New Jersey turned to solar to cut electricity costs and to burnish its green credentials. The installer opted for power optimizers to reduce wiring and handle shading issues.


Market Forces Keep Solar's Prospects Undimmed By Cheap Oil

Oil prices are tangential at best in their relationship to practical considerations in the solar sector. Regulatory issues and dynamics of the maturing energy market are much more important.

PV America_id1480
Hybrid Energy Innovations 2015
Gamechange Racking_id1491
Solectria_id1450